The quote is a spreadsheet, and the job is somewhere else
The estimate was built once, in a file. The material is bought and the hours are worked in other places, so nobody compares the two until the job is over.
PROJECT PLANNING AND JOB COSTING
Miridia Projects is the project planning and job costing module of the supply chain automation platform. It plans each job in phases, prices it line by line as material, labour and other costs, and draws the material from your stock as the work uses it. The forecast cost, the forecast end date and a health flag move with every actual.
WHAT GOES WRONG
The estimate was built once, in a file. The material is bought and the hours are worked in other places, so nobody compares the two until the job is over.
The cost of a job that runs 12% over shows up when the supplier invoices arrive and the hours are added up. By then the work is finished and the price is agreed.
A technician takes cable and fittings from the shelf. The stock count drops, and nothing says which job used it, so the job looks cheaper than it was.
The first phase finishes three days late. The end date on the plan stays where it was, and the customer is promised a date that cannot hold.
HOW IT RUNS
Name the customer, the site and the manager, and set the budget and the contingency. Add the phases, each with planned dates.
Add cost lines to each phase as material, labour or other. A labour line holds its hourly rate, and a material line names the product from your catalogue.
Record the hours, the other costs and the material used. A material actual takes the stock out of inventory in the same step, so the stock and the job always agree.
The planned cost, the actual cost, the forecast at completion, the variance against the budget and the forecast end date are live. The project shows On track, Watch or At risk.
THE PLATFORM
Each project has a customer, a site, a manager, a budget and a contingency. The budget is the number that the forecast is measured against.
Split a job into phases with planned and actual dates and a progress figure. Move the dates of a phase, and the forecast end date of the project follows.
Plan each phase in cost lines. A material line names a product, a labour line holds its rate, and an other line carries anything else that the job costs.
Record an actual against a cost line. A material actual draws the stock from inventory in the same step, with the movement on the ledger and the job on the movement.
Miridia takes the actual cost, adds the planned cost of the work that remains, and adjusts it by how the finished phases ran against plan. The variance against the budget updates as you record.
A project is At risk when its forecast cost passes the budget, and on Watch when more than half of the contingency is used. Filter the portfolio by health to see which jobs need a call.
List every project with its budget, its forecast and its health, or switch to a timeline that shows every open project on one Gantt chart.
Each project has a timeline of its phases and a cumulative cost chart, with the actual cost and the forecast on one date axis.
A job that needs a fabricated part links to the work order that makes it. The work order stays a normal work order, with its bill of materials and its stock movements.
Every change is on the activity record of the project. Add comments and attach quotes, photos and site notes to the project itself.
HONEST FIT
QUESTIONS
It is the project planning and job costing module of Miridia. A project has phases, cost lines for material, labour and other costs, and actuals. It gives a live forecast of the cost and of the end date.
Yes. A material actual draws the stock out of inventory in the same step. The movement is on the ledger with the project on it, so the stock count and the cost of the job agree.
It adds the actual cost to the planned cost of the work that remains, and adjusts that figure by how the finished phases ran against their plan. The variance against the budget is the forecast minus the budget.
A project is At risk when its forecast cost is above its budget. It is on Watch when more than half of its contingency is used. Otherwise it is On track.
Each labour cost line holds its own hourly rate. Hours that you record against the line are costed at that rate.
Yes. A project links to the work orders that make parts for it. The work orders keep their bills of materials and their stock movements.
It is an add-on to your subscription, like Miridia Flows. Book a consult and we will show it on your own jobs.
MAKE. MOVE. MEASURE.
Bring a recent quote and what the job cost in the end. We load it into a demo account and show where the forecast would have warned you.